Construction of Patuakhali (Payra) - Gopalganj 400 kV Transmission Line & Gopalganj 400 kV Grid Substation

Objective(s) • To create necessary facilities to evacuate power from upcoming coal based payra 1320 MW Power Plant
Scope of Work a) Patuakhali(Payra)- Gopalganj 400 kV Double circuit transmission line: 160 km (including 7 km river crossing)
b) 132 kV double circuit line LILO of Madaripur –Gopalganj(Old) at Gopalganj (New) substation: 8km
c) 132 kV double circuit line LILO of Madaripur –Faridpur at Gopalganj (New) substation: 1km
d) Gopalganj 400/132 kV AIS Substation: 01 Nos (Total 3x325 MVA)
Project Cost Total : 329424.46 Lakh BDT; GoB : 270774.79 Lakh BDT; PA: 34871.26 Lakh BDT; PGCB : 23778.41 Lakh BDT
Development Partner ADB
Present Status Physical: 98.75% Financial: 68.93%
Estimated Duration January, 2017 to June, 2023
Project Office Project Director : Morshed Alam Khan, Superintending Engineer
Project Office : NLDC Complex Bhaban, Aftabnagar, Badda, Dhaka- 1212
Mobile : 01799985286
E-mail : pd.pgp@pgcb.gov.bd

last updated on: 2022-09-29 07:32:32
Information Source: Project Planning